RATAWI AGUP Phase 1 – Overhead Power Line from National Grid to CPF1

Boabat Alnoor executed the EPC delivery of the 33 kV OHTL connection from the National Grid to CPF1 for TotalEnergies in Ratawi, utilizing advanced ACCC Casablanca Conductors across 26 steel towers and integrating a 31.5 MVA mobile substation.

Boabat Alnoor Company (BN) delivered the turnkey Engineering, Procurement, and Construction (EPC) contract for the RATAWI AGUP Phase 1 transmission line project in Basra, Iraq, for TotalEnergies EP Ratawi Hub (TEEPRH)[cite: 8]. The infrastructure development establishes a direct, high-capacity electrical link from the Iraqi National Grid to Central Processing Facility 1 (CPF1), securing stable and reliable utility power for critical upstream facilities within the Ratawi Oil Field[cite: 8].

Scope

The contract delivered a full EPC transmission and substation package across challenging desert oilfield terrain[cite: 8]:

  • Route alignment, detailed engineering, and foundation design accommodating multiple oilfield pipeline, road, and utility crossing corridors[cite: 8].
  • Turnkey procurement and delivery of high-capacity ACCC conductors, galvanized steel lattice structures, composite insulators, and high-voltage line hardware[cite: 8].
  • Civil foundation construction, reinforced concrete works, and soil stabilization across soft desert right-of-way sections[cite: 8].
  • Assembly and erection of heavy-duty suspension, angle, and tension steel lattice towers[cite: 8].
  • Specialized tension stringing, sagging, and termination of advanced composite-core ACCC Casablanca conductors[cite: 8].
  • Site installation, connection, and tie-in works for a high-capacity 31.5 MVA, 132/33 kV mobile substation[cite: 8].
  • Execution of the critical 132 kV T-Tap transmission connection to interface directly with the national transmission grid[cite: 8].
  • Comprehensive testing, pre-commissioning, high-voltage insulation checks, and energized network handover[cite: 8].

Key Deliverables & Advanced Technology

The project highlights the implementation of high-efficiency, advanced conductor technologies in oil and gas infrastructure[cite: 8]:

  • Transmission Line: Approximately 6 km of 33 kV overhead transmission line (OHTL)[cite: 8].
  • Advanced Conductor: High-performance ACCC® Casablanca Conductors manufactured by EMTA under CTC Global license, delivering high ampacity and minimal thermal sag over pipeline corridors[cite: 8].
  • Tower Structures: 26 hot-dip galvanized steel lattice towers, comprising engineered suspension, heavy-angle, and terminal tension configurations[cite: 8].
  • Substation & Grid Tie-In: Installation and integration of a 31.5 MVA, 132/33 kV mobile substation and complete 132 kV T-Tap line tap-off connection[cite: 8].
  • Hardware & Insulation: Certified transmission line hardware fittings supplied by Sicame and high-spec outdoor composite insulators supplied by SolidCure[cite: 8].

How it is delivered

Constructed in close coordination with TotalEnergies operational teams, works were executed under stringent international oilfield HSE regulations and strict permit-to-work (PTW) protocols[cite: 8]. Tension-stringing operations over active hydrocarbon pipelines and crossing corridors were managed with engineered protection scaffolds to ensure zero risk to surrounding live assets[cite: 8].

Rigorous quality controls—including conductor core verification, torque checks, insulator testing, and substation protection scheme validation—ensured flawless energisation and immediate grid synchronization[cite: 8].